Corridor access
Third Party Works
Applications, initial-response deadlines and approval progress.
UGLRL Third Party Works
End-to-end works process
Every UGLRL third party works approval follows one of four pathway categories, from application lodgement through to case close-out. Scroll to follow the full process — each stage lists its accountable lane, the published target duration, and any decision or information loop.
Minor Project — Direct Approval (Category 1)
10 stagesDeed Poll issued by UGLRL under its own delegation.
Direct approval
TPW application submitted
ApplicantReview documentation received — determine if the application can be approved by UGLRL
O&M Contractor (UGLRL)No → follow Minor Project Principal Approval (Category 3)
Prepare Approval Brief, Licence Plans & collect fees
O&M Contractor (UGLRL)Two (2) business daysProgress internal SP stakeholder clearances
O&M Contractor (UGLRL)One (1) weekAdditional information required by SP stakeholders? Yes → applicant to provide further information
Information loop back to applicant (SP stakeholders)
Finalise Approval Brief and send for peer review
O&M Contractor (UGLRL)24 to 48 hoursSend Approval Brief for internal signing
O&M Contractor (UGLRL)One (1) dayUGLRL approved
O&M Contractor (UGLRL)Prepare draft Deed Poll and send for legal review if amendments or special conditions apply
O&M Contractor (UGLRL)Two (2) daysIssue Deed Poll to applicant for signing
O&M Contractor (UGLRL)Update relevant databases (insurances, revenue collection) and close application
O&M Contractor (UGLRL)One (1) day
Minor Project — Direct Consent (Category 2)
13 stagesPrecedent Letter signed by the applicant, then Consent Letter issued by UGLRL.
Direct consent
TPW application submitted
ApplicantReview documentation received — determine if the application can be approved by UGLRL
O&M Contractor (UGLRL)No → follow Minor Project Principal Approval (Category 3)
Prepare Approval Brief, Licence Plans & collect fees
O&M Contractor (UGLRL)Two (2) business daysProgress internal SP stakeholder clearances
O&M Contractor (UGLRL)One (1) weekAdditional information required by SP stakeholders? Yes → applicant to provide further information
Information loop back to applicant (SP stakeholders)
Finalise Approval Brief and send for peer review
O&M Contractor (UGLRL)24 to 48 hoursSend Approval Brief for internal signing
O&M Contractor (UGLRL)One (1) dayUGLRL approved
O&M Contractor (UGLRL)Draft Precedent / Consent Letters and send to the Senior Third Party Works Officer for review
O&M Contractor (UGLRL)24 to 48 hoursSend Precedent Letter for internal signing
O&M Contractor (UGLRL)One (1) dayIssue Precedent Letter to applicant for signing
O&M Contractor (UGLRL)Signed Precedent Letter received — send Consent Letter for internal signing
O&M Contractor (UGLRL)One (1) dayIssue Consent Letter to applicant
O&M Contractor (UGLRL)Update relevant databases (insurances, revenue collection) and close application
O&M Contractor (UGLRL)One (1) day
Minor Project — Principal Approval (Category 3)
13 stagesTfNSW approval followed by an executed Legal Agreement.
Principal approval
TPW application submitted
ApplicantReview documentation received — determine if the application is to be approved by TfNSW
O&M Contractor (UGLRL)No → follow UGLRL Direct Approval (Cat 1) or Direct Consent (Cat 2)
Determine if the application can be approved without TfNSW approval (MAD, LAAN, non-intrusive etc.)
TfNSWPrepare Approval Brief, Licence Plans & collect fees
O&M Contractor (UGLRL)Two (2) business daysProgress internal SP stakeholder clearances
O&M Contractor (UGLRL)Two (2) weeks, except LAAN three (3) daysAdditional information required by SP stakeholders? Yes → applicant to provide further information
Information loop back to applicant (SP stakeholders)
Finalise Approval Brief and send for peer review
O&M Contractor (UGLRL)24 to 48 hoursSend Approval Brief for internal signing
O&M Contractor (UGLRL)One (1) daySubmit Approval Brief to TfNSW
O&M Contractor (UGLRL)TfNSW approval
TfNSWTwo (2) weeksNot approved → additional information required by TfNSW
Information loop back to applicant (TfNSW)
Prepare draft Legal Agreement and send to TfNSW Legal for review
O&M Contractor (UGLRL)Two (2) weeksIssue Legal Agreement to applicant for signing
O&M Contractor (UGLRL)Arrange for execution of the Legal Agreement in accordance with delegations
O&M Contractor (UGLRL)48 hoursUpdate relevant databases (insurances, revenue collection) and close application
O&M Contractor (UGLRL)One (1) day
Major Project (Category 4)
35 stagesAIP Letter with design and construction gateways, executed Legal Agreement, then gated construction to asset acceptance.
Approval in Principle (AIP)
TPW Approval in Principle (AIP) application submitted
ApplicantReview documentation received
O&M Contractor (UGLRL)Two (2) business daysDetermine if Landowner’s Consent is required — LoC process to be followed and included in the AIP approval brief
O&M Contractor (UGLRL)Appoint SP Liaison Officer and notify TfNSW of the Major Project
O&M Contractor (UGLRL)Prepare Approval Brief & Licence Plans and collect fees
O&M Contractor (UGLRL)Two (2) business daysInitial briefing of internal SP stakeholders and progress stakeholder clearances
O&M Contractor (UGLRL)Two (2) weeksAdditional information required by SP stakeholders? Yes → applicant to provide further information
Information loop back to applicant (SP stakeholders)
Gateway Two (2) submission to UGLRL CCB to agree the assurance plan, including design gateway reviews
O&M Contractor (UGLRL)Facilitate Joint Inception Meeting with UGLRL / TfNSW — TfNSW appoint a Project Lead and notify SP
O&M Contractor (UGLRL)Submit AIP Brief to TfNSW
O&M Contractor (UGLRL)TfNSW approval
TfNSWTwo (2) weeksNot approved → additional information required by TfNSW
Information loop back to applicant (TfNSW)
Issue AIP Letter including design / construction gateways, other requirements and legal agreement/s — close AIP application
O&M Contractor (UGLRL)Applicant receives approved AIP Letter
Applicant
Construction approval
Applicant responds to AIP / CCB conditions and submits the assurance plan for the next stage
ApplicantAssurance plan approved and conditions closed
O&M Contractor (UGLRL)Design development and design reviews at 30%, 70% and 100% by the appointed TAO — submit evidence at agreed hold points
ApplicantReview and acceptance of progressive evidence at agreed hold points
O&M Contractor (UGLRL)Applicant submits construction application with IFC designs and assurance evidence per the agreed assurance plan
ApplicantProgress internal SP stakeholder clearances
O&M Contractor (UGLRL)Two (2) weeksAdditional information required by SP stakeholders? Yes → applicant to provide further information
Information loop back to applicant (SP stakeholders)
Book CCB meeting and inform applicant
O&M Contractor (UGLRL)Gateway Three (3) submission to UGLRL CCB for approval to proceed to construction and to agree the next-stage assurance plan
ApplicantConstruction approval granted by CCB and construction assurance plan approved
O&M Contractor (UGLRL)Submit Construction Licence Approval Brief to TfNSW
O&M Contractor (UGLRL)TfNSW approval, including the terms of the Legal Agreement
TfNSWTwo (2) weeksNot approved → additional information required by TfNSW
Information loop back to applicant (TfNSW)
Construction Licence Approval Brief approved
O&M Contractor (UGLRL)Prepare draft Legal Agreement and send to TfNSW Legal for review
O&M Contractor (UGLRL)Two (2) weeksIssue Legal Agreement to applicant for signing
O&M Contractor (UGLRL)Arrange for execution of the Legal Agreement in accordance with delegations — TfNSW issue invoice per approved variation / known costs
O&M Contractor (UGLRL)48 hoursUpdate relevant databases and close construction application
O&M Contractor (UGLRL)One (1) day
Construction delivery
Applicant progresses to construction
ApplicantSP Liaison Officer coordinates with the applicant for planned monitoring activities per the agreed assurance plan
O&M Contractor (UGLRL)Hold points reviewed and signed off during construction
O&M Contractor (UGLRL)Hold points / licence conditions not satisfactorily completed → implement corrective action
Construction completion
ApplicantGate Five (5) CCB presentation to accept the completed asset
O&M Contractor (UGLRL)SP Liaison Officer notifies the Principal Property Manager on completion of works
O&M Contractor (UGLRL)Project closure advice received and accepted by TfNSW
TfNSW